Cleaner, greener Cambridgeshire County Council on target for net zero by 2030

Avatar photo

Published

on

Cambridgeshire County Council says it is on track to reach its organisational net zero goal for its direct emissions by 2030. Councillors on the environment and green investment committee heard the news today (Thursday) in its annual carbon footprint report.

“This year’s report shows that direct emissions from the county council’s own assets are down 42 per cent compared to 2018-19 figures,” said a council spokesperson.

“This marks the sixth time the organisation’s carbon impact has been outlined to politicians.

“Over the last financial year, the county council as an organisation has been directly responsible for less than 1000 tonnes of tCO2e. ‘tCO2e’ means ‘tonnes of carbon dioxide equivalent’ and is the formal measure for greenhouse gases (GHGs) which make up environmentally harmful emissions.”

The carbon footprint report also estimates the council’s indirect carbon emissions created through its supply chain and operations.

The county council provides a range of services such as education, road maintenance and waste disposal which involve a wide range of businesses and suppliers.

Cambridgeshire County Council is using the new Shire Hall HQ carports as one example of its net zero goal. The solar carports which provide electricity to the building alongside the rooftop solar photovoltaic panels on top of New Shire Hall. The carports power EV charging points. IMAGE: RG Carter

Cambridgeshire County Council is using the new Shire Hall HQ carports as one example of its net zero goal. The solar carports which provide electricity to the building alongside the rooftop solar photovoltaic panels on top of New Shire Hall. The carports power EV charging points. IMAGE: RG Carter

The spokesperson said it is estimated that indirect emissions, excluding the rural estate, were around 111,000 tCO2e – 39 per cent lower over the last financial year than in the baseline year of 2018-19.

“The ongoing reduction in direct emissions is due to a programme of retrofitting works and low carbon heating projects which has involved new insulation, LED lighting and other measures introduced in many of our buildings,” said the spokesperson.

“As well as fossil fuel-based heating systems (like gas or oil boilers) replaced with low-carbon air source heat pumps.”

Cambridgeshire County Council is using the new Shire Hall HQ carports as one example of its net zero goal. The solar carports which provide electricity to the building alongside the rooftop solar photovoltaic panels on top of New Shire Hall. The carports power EV charging points. IMAGE: RG Carter

Cambridgeshire County Council is using the new Shire Hall HQ carports as one example of its net zero goal. The solar carports which provide electricity to the building alongside the rooftop solar photovoltaic panels on top of New Shire Hall. The carports power EV charging points. IMAGE: RG Carter

The council says retrofit works have taken place over the last year at council buildings including March Community Centre, Tennyson Lodge and St Neots library bringing the total number of buildings retrofitted up to 25.

The council buys electricity through a zero-carbon tariff for all its buildings and street-lighting.

The authority also generates clean electricity on some buildings from on-site solar panels.

Further research is underway to assess the council’s indirect GHGs and how it can continue to reduce emissions.

The spokesperson said: “On our rural estate we are undertaking surveys and workshops with our farm tenants to understand and encourage sustainable farming practices and highlight best practices.

Cambridgeshire County Council is using the new Shire Hall HQ carports as one example of its net zero goal. The solar carports which provide electricity to the building alongside the rooftop solar photovoltaic panels on top of New Shire Hall. The carports power EV charging points. IMAGE: RG Carter

Cambridgeshire County Council is using the new Shire Hall HQ carports as one example of its net zero goal. The solar carports which provide electricity to the building alongside the rooftop solar photovoltaic panels on top of New Shire Hall. The carports power EV charging points. IMAGE: RG Carter

“Meanwhile, council suppliers are being encouraged to sign up to our Climate Charter, with 47 companies having agreed to take action on their own GHG emissions so far.”

The committee also heard an update on the progress of the council’s actions as an energy generator.

The council runs its own solar farm in Soham and a range of further renewable energy initiatives have been delivered or are in progress including smart microgrids at Park & Ride sites and the roll out of UK’s first rural heat network at Swaffham Prior.

Advertisements
canopyuk.com in-article

“When all the county’s renewable projects are considered over their expected lifetime, the council is estimated to contribute more than 15 GWh to the grid,” said the spokesperson.

Cllr Lorna Dupre, chair of the environment and green investment committee, said: “It’s fantastic to hear about the progress we’ve been making towards our visions for a greener Cambridgeshire.

“There’s no doubt that our work is paying off in reduced emissions and lower energy costs, meaning we can ensure more of our budget is spent on critical statutory services like caring for the more vulnerable in our society.”

Cambridgeshire County Council is using the new Shire Hall HQ carports as one example of its net zero goal. The solar carports which provide electricity to the building alongside the rooftop solar photovoltaic panels on top of New Shire Hall. The carports power EV charging points. IMAGE: RG Carter

Cambridgeshire County Council is using the new Shire Hall HQ carports as one example of its net zero goal. The solar carports which provide electricity to the building alongside the rooftop solar photovoltaic panels on top of New Shire Hall. The carports power EV charging points. IMAGE: RG Carter

“However, we also recognise that we have a long way to go, which is why I’m pleased to see us influencing our suppliers to make environmental changes and empowering council staff to make changes to help us ensure we achieve our net zero goal target by 2030.”

Data was also presented to the committee outlining Cambridgeshire’s ‘journey to green’.

Unlike the latest council information, the most recent data available across the UK’s geographic counties is collated by central government and is from 2022.

A midpoint target will be discussed to help the area become a Net Zero county by the council’s ambitious target of 2045 – five years ahead of the legally binding national commitments.

Case Study: New Shire Hall HQ Carports

The council’s Alconbury Weald-based HQ has solar carports which provide electricity to the building alongside the rooftop solar photovoltaic panels on top of New Shire Hall.

The carports power EV charging points for the council’s pool cars and charging points are also available at a competitive rate to staff and visitors.

The carports exported more than £50,000 worth of electricity in 2023-24 and are projected to provide £1.5m worth of electricity during the infrastructure’s lifetime.

Case study: Schools

There is an ongoing education buildings retrofit programme to help county schools save carbon and cut energy bills. Works have involved installation of LED lighting and solar photovoltaic panels. Over the past 3 years works have also included installation of air source heat pumps.

So far it is estimated that the 69 schools involved have saved a combined total of over £5.8m on their energy bills.

Over the lifetime of the works, it is estimated the schools will have avoided around £26m in energy costs which would otherwise have had to be found from the school budget.

FACT FILE

RG Carter says they were ‘very proud to have been entrusted to design and deliver, from ROBA Stage O to construction, the new home for Cambridgeshire County Council, New Shire Hall.

“Delivering environmental excellence, this modern, flexible building has now been handed over, ready to provide efficient work space to the council staff and improve access to the heart of the council’s democratic functions”. New Shire Hall opened in 2022

Facebook

Read More

News18 hours ago

Former world champion Nigel Mansell welcomes Cambridge teenage racer to youth charity

Ex-Formula 1 World Champion Nigel Mansell has been joined by Cambridge teenage racer Nickolas Ellis at UK Youth, Great Britain’s...

News20 hours ago

Threat to close £32m King’s Dyke crossing at Whittlesey if movement and cracking intensifies

Full closure of the £32m King’s Dyke Crossing at Whittlesey is on the table “if there is a change to...

Crime2 days ago

WATCH: Wisbech drug dealer caught with imitation firearm

A drug dealer from Wisbech who was found carrying an imitation firearm has been jailed. Miguel Mota, 18, was stopped by...

Crime2 days ago

Fenland man jailed for ignoring order to stop stalking ex-partner

A stalker who tried to pressure his former partner into dropping court action against him has been jailed.  John Cassidy,...

News2 days ago

Skylark Garden Centre and Café to close for day of owner’s wife funeral

Skylark Garden Centre and Café at Wimblington will close on October 23rd for the day for the funeral of Melanie...

News2 days ago

East Cambs Council refutes ‘bias’ claims over 540 homes at Soham

A council refuted claims that two councillors should have excluded themselves from taking part in a planning committee meeting that...

News3 days ago

Cambs couple celebrate diamond anniversary with a party and a card from the King

A couple living at Jubilee Court retirement community in March, have celebrated their diamond wedding anniversary with friends and loved...

Crime3 days ago

Man calls Cambridge hotel housing immigrants ‘be ready, we’ll be coming for them’

A man who phoned a Cambridge hotel to threaten asylum seekers has been handed a five-year criminal behaviour order. Robert Shortman,...

News3 days ago

Cambridgeshire County Council rejects early review of 20mph speed limit for Ely

A 20mph speed limit will remain in Ely and not reviewed for two years, Cambridgeshire County Council has told Cllr...

News3 days ago

Cambridgeshire man among victims of M6 crash which killed five

A man from Cambridgeshire was among five people – including two children – killed in a crash on the M6...